With successful completion and delivery of high school Orchlon became the first high school in Mongolia that offers S.T.E.A.M program through its new facilities and laboratories (Science, Technology, Engineering, Art & mathematics in relation to the Cambridge program.
The high school with capacity of 500 students had unique architectural and engineering design with its 32m span overhead bridge connection to the main facility and the façade that has both modern and cultural perceptions.
It has been great achievement for the project team to successfully complete the delivery the project to the client within 7 months from the commencement.
Mostly important, LTI free 328’762 hours were spent on projects.
Location: Khan-Uul District, Ulaanbaatar, Mongolia.
Client: Orchlon International School LLC.
Contract Type: Construction Main Contractor, Design Author.
CFA: 8’062м2
Manhour: 1’292’647
Timeframe: 2019.03-2019.11